An Empirical Analysis of the Interconnection Queue
Electricity generation projects seeking to connect to the U.S. power grid go through an interconnection queue, where a sequence of engineering studies determines each project’s interconnection cost. Most projects that begin the process do not complete it. Using new data, we find that a long queue delays the necessary engineering studies. We develop and estimate a dynamic equilibrium model in which entry, waiting, withdrawal, completion, and queue congestion are jointly determined, and quantify the effects of policy reforms. Speeding up study delivery by 50% raises completed generation capacity by 32%. Increasing the cost of entering the queue has little effect on waiting time or completed capacity, because it primarily deters projects that would spend little time in the queue and therefore contribute little to congestion.
-
-